Parsons
Report
Executive Summary
1.1
Introduction
Parsons was retained by the Salton Sea
Authority to perform an independent technical review and critique the
Phase 1 alternatives described in the Draft Salton Sea Restoration Project
Environmental Impact Statement/Environmental Impact Report (EIS/EIR).
Fatal flaws, as well as possible refinements, in the alternatives
were to be identified. Possible
Phase 2 actions/concepts were to be briefly evaluated, primarily from a
cost-effectiveness point of view. In
addition, other possible salinity and elevation control actions were to be
identified and suggestions for further analysis were to be made.
URS Greiner Woodward Clyde, Jones &
Stokes, and John A. Pyles were key members of a team assembled by Parsons
to conduct the above analysis.
Generally, URS performed a review of the
in-Sea dike design proposed in the Salton Sea Restoration Project January
2000 Draft Alternatives Appraisal Report and the costs of the various
concepts and alternatives. Based
on that review, refinements were suggested to reduce seismic risk and
cost. Comments regarding
construction methods for in-Sea dikes were also provided.
Jones & Stokes evaluated the Bureau's
water and salt accounting model for suitability in determining if
alternatives can effectively meet the salinity and elevation goals
established for the restoration project. They also used the model to
review the effectiveness of the Draft EIS/EIR alternatives and to assist
in identifying concepts for review and evaluation.
Mr. John A. Pyles, a retired Cargill Salt
employee, focused primarily on the solar salt removal (and disposal)
concepts proposed in the Draft Appraisal Report and provided an in-sight
into the chemical properties of Salton Sea water and their effect on salt
removal and disposal. Building
upon the ideas of the Salton Sea Authority Executive Director, he
developed a concept for removal of salt in a series of solar evaporation
ponds and disposal in separate crystallizer ponds.
Parsons coordinated the work and kept the
team focused on the big picture. In
addition, Parsons suggested refinements to the alternatives, developed
alternatives and concepts for further evaluation, and performed much of
the cost-effectiveness analysis.
This study
focused on the technical and engineering aspects of the water and salt
management alternatives described in the Draft EIS/EIR and Draft Appraisal
Report. No evaluation of the
potential environmental effects of the Draft EIS/EIR alternatives or of
the suggested modifications to the Draft EIS/EIR alternatives was
performed. It was assumed
that the environmental effects of the recommendations contained in this
report will be addressed as the preferred restoration project evolves.
1.2
Approach
The Parsons Team met with the Salton Sea
Authority in La Quinta, California and with the Bureau of Reclamation in
Denver, Colorado to gather background, key documents, and other supporting
information. In addition,
members of the Parsons Team toured the Salton Sea to gain additional
understanding and information.
The Draft Appraisal Report and the Draft
EIS/EIR were used extensively in our evaluation. Other supporting
information was also used in our analysis.
Practical experience in building in-Sea dikes and other facilities,
water and salt modeling, salt making, and similar projects was melded into
our work.
The Team's experience with designing and
constructing in-Sea dikes, dams, and other facilities combined with the
perspective contributed by Mr. John A. Pyles led to the development of
concepts for using solar evaporation ponds in a more effective manner for
salt removal and disposal.
The Bureau provided a copy of its water
and salt accounting model to the Team.
The model was reviewed for suitability and used to analyze the
effectiveness of the Draft EIS/EIR alternatives.
The model also helped the Team to understand the interrelationship
between salinity changes and elevation changes more easily.
1.3
Conclusions and Recommendations
The Salton Sea Authority and the Bureau
of Reclamation with input and guidance from the Salton Sea Authority Board
and Technical Advisory Committee and the Salton Sea Science Subcommittee
have devoted significant time and effort to the Salton Sea Restoration
Project and produced a considerable amount of information. The information
gathered, the documents produced, and the public participation process has
provided the foundation for completion of appraisal level studies and
initiation of more detailed evaluations that can lead to selection of a
preferred project for the Final EIS/EIR.
Our more significant conclusions and
recommendations, based on a review and analysis of available data, are
listed below. These conclusions and recommendations are discussed in the
body of the report. Other
less significant conclusions and recommendations are contained in the
report itself.
1.3.1
Conclusions
The water and salinity accounting model
and the assumptions used in the model provide a suitable tool for
evaluating the effectiveness of proposed alternatives for meeting salinity
and elevation goals established for the Salton Sea.
Each of the Phase 1 Draft EIS/EIR
alternatives can meet the elevation and salinity goals within 40 years of
implementation.
If the inflows to the Sea are ultimately
reduced to 0.8 million acre-feet per year (MAF/yr.) additional replacement
inflows and/or displacement facilities will be required to meet the
current salinity and elevation goals.
The south pond would remove essentially
the same surface area from the Salton Sea as the displacement dike for
about one-half the estimated cost (about $195 million versus $450
million).
The in-Sea north and south ponds and the
displacement dike (as currently designed for the proposed operation) are
very vulnerable to damage or failure due to a major seismic event.
If the north and south in-Sea ponds (and
the displacement dike) are constructed as proposed, they should be
operated with water on both sides of the dike to reduce the vulnerability
to seismic events. To reduce consequences of possible breaching, water on
the pond side should be slightly lower than the Sea.
A displacement dike can be designed and
constructed to be dry on one side. A
conceptual design is provided in this report.
Low in-Sea dikes are considerably less
costly than tall in-Sea dikes and less vulnerable to earthquakes.
For example, a 17-foot high dike would cost about one-third as much
per linear foot as a 35-foot high dike.
Onshore dikes would cost considerably
less per linear foot than in-Sea dikes, assuming the same height and good
foundation conditions.
A series of solar evaporation ponds are
more effective for evaporating Salton Sea water and removing salt than a
single deep pond.
The single deep ponds, if constructed,
should be operated as the first solar evaporation pond in a series with
separate salt disposal ponds and/or an EES to increase the life expectancy
and efficiency of the ponds.
Enhanced Evaporation Systems (EES)
accelerate evaporation, but are not currently used by the salt industry to
make salt because the annual operation, maintenance and replacement costs
are much higher than for solar evaporation ponds.
Use of Colorado River flood flows (if
they are available) and Central Arizona Salinity Interceptor (CASI) water
(if it becomes available) are much more cost-effective than other methods
of obtaining replacement inflows or reducing the amount of inflow needed
to stabilize the elevation of the Sea.
Exporting Sea water to the Pacific Ocean
or the Gulf of California is an effective but prohibitively expensive way
to remove salt from the Sea.
Importing Pacific Ocean or Gulf of
California water to the Sea is not an effective way to reduce or control
the Sea’s salinity or water elevation.
The salt content of the Pacific Ocean and/or the Gulf of California
water is too high.
Higher salinity and lower elevation goals
would reduce the size and cost of the actions or concepts needed to
achieve and maintain salinity and elevation goals.
1.3.2
Recommendations
An evaluation of alternative(s) using a
series of solar evaporation (onshore and/or in-Sea) ponds with onshore
salt disposal and bittern disposal ponds should be made.
Because of construction cost, priority in
evaluation should be given to onshore solar evaporation ponds, followed by
shallow in-Sea and then deep in-Sea ponds.
Consideration should be given to
potential displacement benefits from in-Sea ponds and to using deeper
ponds to dispose of bittern while using the surface of the ponds to
evaporate Sea water.
If insufficient land is available and/or
solar evaporation ponds cannot be constructed for a reasonable cost,
consideration should be given to using an EES in conjunction with solar
evaporation ponds.
Borings should be performed along the
alignment of all in-Sea dikes selected for detailed analysis to determine
foundation material properties and to verify and refine costing
assumptions.
A preliminary earthquake response
evaluation should be performed on the proposed in-Sea dike designs to
analyze and predict potential deformation modes.
Soil percolation data should be obtained
for those sites where onshore ponds may be constructed.
Leakage will affect the amount of pond area needed to achieve a
certain rate of salt removal.
A series of small solar evaporation test
ponds should be constructed and operated at the Salton Sea to obtain data
for preliminary sizing and development of the solar evaporation pond
concepts.
The evaporation rate of Salton Sea water
is needed so that the size of the evaporation ponds can be refined.
The volume of salt produced and its
density are needed so that the size of salt disposal facilities can be
refined.
The characteristics of the bittern are
needed to determine if it will dry out and if it can be disposed of in the
bottom of deep evaporation ponds without interfering with the evaporation
rate.
An evaluation of the cost of dredging the
Sea's bottom and depositing the dredged material at the shore for creation
of shallow ponds and/or displacement of Sea surface area should be made.
The feasibility and cost-effectiveness of
fallowing should be evaluated for maintaining Sea inflows instead of, or
until CASI water is available.
EES should be pilot tested to obtain
better annual cost data and confirm area requirements and evaporation
rates. An EES demonstration
plant should be constructed and operated for at least a year to refine
pilot plant data for final design if the EES is part of the project
alternative.
A review of the Sea's elevation and
salinity goals should also take place before completion of the Final EIS/EIR.
A salinity range of 35 to 40 ppt and an elevation range of -230
to -235
feet MSL was previously established; however, a target elevation of -230
feet was recently established. If
the inflow to the Sea decreases, a lower target elevation would require
smaller quantities of replacement inflows and/or smaller displacement
facilities.
[Back to Top
of Page]
Copyright 2000 Salton Sea
Authority - All Rights Reserved
Site Design and Hosting by KG
WebWorks